The project included an analysis and report for issues experienced during the testing and balancing for the 90,000 SF, 2 Story MTF in Aviano, Italy. JPHES was able to identify seventeen air distribution issues as well as potential code violations for air exhaust and intake. All items were identified in a report with recommendations including ductwork modifications, static pressure comparisons, exhaust system redesigns, bio-med exhaust system modification, VAV box modifications and recommended motor replacements. The effort required an extremely flexible schedule as the opening date was on the horizon.
New Crossroads Elementary School, Quantico Marine Corps Base, VA
The new Crossroads Elementary School consolidates three (3) existing elementary schools. It is a transitional 21st Century school with an emphasis on technology and learning through collaboration...